The Spring-Ford Area School Board voted 6-3 on Monday to move forward with a $2.2 million employee health center at 199 Bechtel Road in Upper Providence Township, approving a five-year agreement with Marathon Health LLC, a development budget, and engineering expenditures.
The November 23 decision follows disagreement among board members over the project's financial projections and whether the district should seek competing proposals before entering into an agreement with Marathon Health.
Board members Margaret Wright, Sagar Sharma, and Heidi Goldsmith voted against the measures. Board President Abby Deardorff and members Erica Hermans, David Laky, Karen Weingarten, Theresa Westwood, and Rachael Yudt voted in favor.
During a presentation ahead of the vote, Chief Financial Officer James Fink outlined revised financial projections, estimating that the district could recoup its initial investment in approximately 3.25 years through reduced healthcare claims.
Development Costs and Projected Savings
The estimated $2.2 million development budget accounts for construction, site improvements, equipment, engineering, implementation fees, and potential additional requirements from Upper Providence Township.
Funding will come from roughly $1.43 million in remaining proceeds from the district's 2022 general obligation bond issuance, with an estimated $777,000 drawn from its capital reserve fund. The amount needed from the reserve fund will depend on the final cost of the project.
Fink emphasized that those funds are restricted to capital projects, such as construction and facility improvements, and cannot be used to cover day-to-day expenses like salaries and benefits. However, any healthcare savings generated by the center could help offset those operating expenses.
The administration also negotiated a reduction of about $212,000 in Marathon's first-year operating fees since its August presentation to the board.
The five-year agreement includes a one-time implementation fee not exceeding $129,600, which is included in the development budget, and first-year management fees of $690,732, with annual increases of 3.33 percent. Recurring management fees will not begin until the facility is ready to see patients.
Continued Concerns Over Competitive Bidding
Before voting on a group of financial matters, Wright requested that the board hold a separate vote on the four items related to the health center. She reiterated that while she supported the concept of an employee health center, she opposed moving forward without seeking competing proposals.
“I cannot approve a multi-million dollar project without what I believe to be the important step of an RFP,” Wright said. “I believe that it is negligent and irresponsible, and that we still have time as a board to do what I think is the right thing, which would be to allow this to go out to bid.”
The board split 5-4 in October against seeking competing proposals, leaving Marathon as the only provider under consideration. Yudt, who supported seeking additional proposals in October, voted in favor of moving forward Monday.
Wright also questioned how the district could determine whether Marathon's negotiated fees were competitive. Fink said he used North Penn School District's existing contract with Marathon as a benchmark.
Responding to Wright's concerns about potential underutilization, Fink said an earlier financial analysis indicated that the district could recover its investment over five years with an average health center utilization rate of just 16 to 17 percent. He estimated that the recently negotiated fee reductions could lower that threshold by another one or two percentage points.
Health Center Services and Next Steps
The facility would serve district employees and their dependents enrolled in Spring-Ford's health benefits plan. Staffed by one physician assistant and two medical assistants, the center is expected to offer preventive care, treatment for acute illnesses, immunizations, certain medications, and laboratory services.
Participation would be voluntary, with employees and their families able to continue using their existing healthcare providers. The facility would operate 40 hours per week, with specific hours to be determined in consultation with employees.
The board also authorized up to $110,000 for civil engineering services and $20,000 for mechanical, electrical, and plumbing engineering services, both funded through the remaining 2022 bond proceeds.
Although Upper Providence Township granted conditional use approval in September, the project must still complete the township's land development review and approval process before construction can begin.
Fink estimated that preparing engineering drawings would take about two months, but the overall project timeline remains dependent on the township's review. The Marathon agreement is subject to final review by the school district solicitor's office.